Complete the following fields:
- Run – Displays the selected run option.
- Once – The report will only run once on the selected day, at the selected time.
- Daily – The report will run daily at the selected time.
- Weekly – The report will run weekly at the selected time.
- Monthly – The report will run monthly at the selected time.
- On – Type the day and time on which you want the scheduled report to run.
- At – Type the time at which you want the scheduled report to run; use the 24hr clock: 00:00 to 24:00.
Therefore, Run: Once On: Friday, Aug 01, 2014 At: 08:00 schedules the report to run once only on Friday, August 1, 2014, at 8:00 am.
For more information, please refer to the following articles: